- 150 kV Substation Line Bay for UGC Bontoala and 60 MVA Bay and Transformer in GI Tanjung Bunga, South Sulawesi , First 150 kV Undeground Cable in South Sulawesi.
- 70 kV Transmission Line From Puuwatu – PLTU Nii- Tanaasa , first Transmission Line in Southern Sulawesi .
- 150 kV Substation 4 Line Bay for GI Lopana North Sulawesi.
- 150 kV Substation and Transmission Line for New Tonasa #5 Cement Plant in Pangkep Region South Sulawesi.
- 150 kV Substation 1 Transformer and Bay for GI Pare-Pare South Sulawesi.
- 150 kV Substation 1 Coupler Bay for GI Majene West Sulawesi.
- 70 kV Substation 2 Line bay for GI Talise Central Sulawesi.
- 70 kV Reconductoring Line Pangkep - Mandai South Sulawesi, First Transmission Line using ACCC from CTC (USA) Which carry 2 x Current from normal conductor .
- 150 kV Substation 2 Line Bay For GI Sengkang South Sulawesi 1.
- 150 kV Substation 2 Line Bay and 1 coupler bay GIS and 1 x 60 MVA Transformer, and finishing commisioning for 1 Bay Transformer bay HIS in GI Bontoala South Sulawesi. This project are milestone of first GIS In South Sulawesi and First Hybrid Switchgear From ABB in South Sulawesi
- 150 kV 2 x 25 MVAR Reactor Shunt and bay in Mamuju substation, First Dry Reactor in West Sulawesi.
- 150 kV 2 Line bay , 1 trafo Bay , KIMA Substation , Pilot and first Substation tapping form Single Phi Transmission Line #Sungguminasa project in Indonesia
- 150 kV 11 Line Bay , Bantaeng Substation , Pilot Project Substation for Smelter in South Sulawesi
- 70 kV Reconductoring Transmission Line Pulau Buton – Pulau Muna for 1 , 5 KM Crossing Sea, First succesfull Conducutor ACCC from CTC (USA) Which carry 2 x Current from normal conductor for crossing 1.5 KM Span in Sea . and 50 Meter Height Tower.
- 150 kV Erection 2 x 40 MVA Transformer and Bay in Nii-Tanasa substation , for First PLTMG in Kendari Southern Sulawesi.
- 275 kV Substation Wotu 2 Diameter, Bay Transformer 90 MVA 275/150 kV , first 275 kV Substation in South Sulawesi.